December 2008: Legal Issues

facebooktwittergoogle_plusredditpinterestlinkedinmail

December 2008

Legal Issues

Notice Me

   Information about the Masonry Industry    Information about the Masonry Industry

By Timothy R. Hughes and
Alison R. Mullins

In the terms and conditions of many construction contracts, giving written notice of a possible legal claim for damages is a prerequisite for filing suit later. Lack of proper and timely notice may completely negate a valid claim. A recent decision issued by a Virginia Circuit Court may remove some of the fear from such defenses by adding some flexibility and practicality to the often-rigid written notice requirements in contracts. The court ruled that, because the defendants had actual notice, lack of written notice was not a valid defense.

Lack of written notice, not an excuse
In AMEC Civil, LLC v. Commonwealth of Virginia, the Virginia Department of Transportation (VDOT) awarded a contract for the construction of about four miles of roadway and 11 bridges to AMEC Civil, LLC, as the contractor. Differing site conditions arose throughout performance of the contract. Despite attempts to resolve issues surrounding the differing site conditions, about six years into the contract, the contractor filed a lawsuit against the VDOT alleging breach of contract.

The VDOT argued lack of timely notice barred the contractor’s claims. The contract between the VDOT and the contractor included a provision stating, “Early or prior knowledge by the department of an existing or impending claim for damages could alter the plans, scheduling or other action of the department, or result in mitigation or elimination of the effect of the act objected to by the contractor.” The provision continued to require the contractor to provide written notice “describing the act of omission or commission by the department or its agents that allegedly caused the damages.”

The VDOT bolstered their argument by pointing to statutes requiring notice of claims on state highway projects. The court agreed that the applicable state statutes required written notice. The court cited and agreed, however, with the Supreme Court of Virginia’s holding that, as long as a required act was performed, even if it is not within the statutory time or mode, it will be adequate if the substantial purpose of the statute is accomplished.

The contractor argued the VDOT had actual notice of the claims and, thus, substantially complied with the purpose of both the contractual and statutory provisions for written notice. The VDOT never argued that they lacked knowledge of the contractor’s claims. In fact, the court found that the evidence was clear that the VDOT and the contractor communicated regarding the contractor’s claims during the performance of the contract work. These communications between the parties included meetings, written meeting minutes and memorandum of issues discussed. Further, the court found that the “VDOT did not suffer any prejudice from receiving actual notice as opposed to written notice.”

In making the ruling, the court focused on the underlying purpose of the contract terms and statutory notice. The court found that the documentation of discussions, meeting minutes and claims demonstrated that the VDOT was aware of the contractor’s claims. As such, actual notice satisfied the underlying contract and statutory purposes. Therefore, the contractor’s claims were not barred by failure to provide written notice to the VDOT.

Implications
Best practices dictate strict compliance with all notice provisions whenever possible. Actual circumstances and communications may be enough to demonstrate notice. Context matters greatly as the law from state to state may vary, as may facts from project to project. This is an arena where more is most definitely better.

Conclusion
Knowing your obligations can help you to protect and preserve your legal rights, including enforcement of contractual payment provisions. Failing to send proper and timely notice may bar your claim. While actual notice may be a way around the written notice requirement, as a contractor or subcontractor you should expect and plan for strict enforcement of contractual and statutory requirements for notice of claims and properly preserve your rights.



Return to Table of Contents

Related Posts

  • 36
    January 2011  Legal Issues From Bad to Worse: Keeping Fraud out of Breach of Contract By William Groh Fraud claims can carry potentially severe consequences not ordinarily associated with claims for simple breach of contract, and have increasingly found their way into situations traditionally associated with breach of contract. It…
    Tags: contract, claims, contractor

MASONRY MAGAZINE VIDEO NEWS

Zachary Zuldema 1st Place (2nd Year) Winner Interview at the World of Concrete

Zachary Zuldema 1st Place (2nd Year) Winner Interview at the World of Concrete

Bill Dentinger 2015 Inductee MCAA Hall of Fame

Bill Dentinger 2015 Inductee MCAA Hall of Fame

John Smith, Jr.

John Smith, Jr. receives the 2015 MCAA C. DeWitt Brown Leadman Award

2015 MCAA Fastest Trowel On The Block Winner

2015 MCAA Fastest Trowel On The Block Winner

Daniel Furr 1st Place Winner

Daniel Furr 1st Place Winner (First Year), Masonry Skills Challenge

Synpro Products

Masonry Magazine Video News Interview: Michael Goyne

Hydro Mobile Inc

Interview with Kevin O'Shea of Hydro Mobile, Inc.

Interview with Mark Kemp – Chairman, MCAA

Interview with Masonry Contractors Association of America Chairman, Mark Kemp

Mortar Net Solutions

Interview with Steve Fechino from Mortar Net Solutions

Pullman Ermator

Interview with Lyndon Kelsey of Pullman Ermator

Keene Building Products

Interview with Jim O'Neill of Keene Building Products